Sherpa et al vs Bolloré

Descripción del caso

Fecha archivada 7 December 2010
Estado actual Acuerdo
Asunto Environmental and labour violations at SOCAPALM in Cameroon
Resumen del caso Sherpa, CED, FOCARFE and MISEREOR allege that the Société Camerounaise de Palmeraiess (SOCAPALM), a Cameroonian producer of palm oil, has negatively affected the traditional livelihoods of local communities and plantation workers.

The expansion of SOCAPALMs operations has allegedly diminished the size of local communities and the availability of public services and natural resources, and the company has not contributed to local development, thereby violating its contract with the Government of Cameroon.

The complaint alleges that water and air pollution are not adequately treated, causing problems for both the communities and the environment.
Local villagers also have reported physical abuse by SOCAPALMs security agent Africa Security.
The complainants also allege that SOCAPALMs treatment of plantation workers constituted a breach of the Guidelines. They claim that precarious work is rampant and freedom of association is limited.

Additionally, the housing facilities are deplorable and dividends promised to employees when SOCAPALM was privatised in 2000 were never paid.

The complaint also contends that SOCAPALM has breached the Guidelines Disclosure Chapter by failing to properly disclose relevant information about the company and potential environmental risks.

The French, Belgian and Luxembourgian holding companies Bolloré, Financière du Champ de Mars, SOCFINAL and Intercultures exert joint control over SOCAPALMs operations in Cameroon through complex financial investments.
The complainants allege that these companies have breached the Guidelines by failing to take action to prevent SOCAPALMs negative impact on the environment, local communities, and workers.
Evolución/Resultado The French NCP declared all four cases admissible.

After refusing to cooperate for almost two years, Bolloré indicated a willingness to solve the issues and bring SOCAPALMs operations in line with the Guidelines. Sherpa and Bolloré accepted the NCPs offer of mediation in February 2013.

The NCPs June 2013 final statement concluded that through their business relations with SOCAPALM, all four holding companies violated the Guidelines.

The NCP found that SOCAPALM had breached certain Guidelines relating to general policies, employment and industrial relations, and the environment. The NCP said the companies were not respecting recommendations on information disclosure.

The NCP recommended that the companies find a remedy to the violations, and that they rely on the action plan prepared during the mediation to do so. The action plan covers a range of issues, including community dialogue, reduction of environmental nuisances, public services, local development, workers rights and conditions of work, transparency, and compensation of local communities for their loss of resources and lands.

A procedural issue to note is the complainants insisted on obtaining the NCPs final statement before the end of the mediation, so they could concentrate on the action plan rather than discussing the alleged violations. This approach aimed to clearly differentiate mediation from the process of agreeing to a final statement.

The complainants were pleased that the NCPs statement pointed out the violations, including reviewing each chapter of the Guidelines in relation to these.

In March 2014, the NCP announced in a follow-up statement that the action plan was adopted in September 2013 and that an independent organisation has been selected to monitor its implementation. The NCPs follow-up statement also notes that it should be informed annually about the action plans implementation. The NCP issued a second follow-up communiqué in March 2015 to ask all parties to take responsibility for concrete implementation of the action plan.

Even after the NCPs findings of non-compliance and additional statements, the action plan is not being carried out as planned. The Luxemburg-based holding company, SOCFIN, has refused to implement it, and neither the Luxemburg, the French, nor the Belgian NCP managed to convince the company to honour the agreement. Bolloré has made improvements to its community engagement policy as a result of the case, but the communities have otherwise been left without any form of remedy to date.

The French NCP called on the Belgian and Luxembourg NCPs to take forward their efforts to engage into a dialogue with Socfin for the implementation of the roadmap, while also asking the Bollore Group to reconsider the terms of its relationship with Socfin.

The Belgian NCP then proposed its good office to the Socfin Group, who turned them down. On 5 March 2015, they published a statement expressing its “concern over Socfins refusal of cooperation,” which “means that suitable solutions cannot get underway for the Socapalm workers and local populations.

In early 2016, the Belgian NCP informed the French NCP that Socfin was now prepared to enter into dialogue with it. In its Statement, the Belgian NCP states “Following its statement of 5 October 2015, the Belgian NCP has been approached by Socfin in order to reopen the specific instance referred by four NGOs to the French, Belgian and Luxembourg NCPs since 2010. The Belgian NCP hereby states its agreement with this approach and will ask NGOs to take part in reopening the specific instance.”

The French then transferred the case to the Belgian NCP in early 2016 and finalized its Final Statement on18 May 2016. The case against Socfin remains pending with the Belgian NCP.
Principes directeurs de l’OCDE relacionados
Palabras claves del caso Los derechos laborales, Medio Ambiente, Publicación de informaciones, Sector forestal, Más de un PNC

Información PNC

Nombre PNC National Contact Point France
Dirección PNC Rue de Bercy 139 75572 Paris, Cedex 12, France
Sito web del PNC www.minefi.gouv.fr/directions_ser
Otras PNCs comprometidos

Demandadores

ONG

Información de la empresa

Empresa responsable Bolloré S.A
Dirección de la empresa Sise Odet
29 500 Ergué Gabéric
France
Sito web de la empresa
Empresa en violación Bolloré S.A
Pais de operaciones Camerún
Otras empresas comprometidos

Cronología del desarollo

Fecha Actor Acción Descripción Documento
18 May 2016 National Contact Point France declaración After the roadmap failed to operationalize, the French NCP called on the Belgian and Luxembourg NCPs to take forward their efforts to engage into a dialogue with Socfin for the implementation of the roadmap. After the Belgian NCP proposed its good office to the Socfin Group, who turned them down, the Belgian NCP published a statement in 2015 expressing its “concern over Socfins refusal of cooperation,” which “means that suitable solutions cannot get underway for the Socapalm workers and local populations. In early 2016, the Belgian NCP informed the French NCP that Socfin was now prepared to enter into dialogue with it. In its Statement, the Belgian NCP states “Following its statement of 5 October 2015, the Belgian NCP has been approached by Socfin in order to reopen the specific instance referred by four NGOs to the French, Belgian and Luxembourg NCPs since 2010. The Belgian NCP hereby states its agreement with this approach and will ask NGOs to take part in reopening the specific instance.” The French then transferred the case to the Belgian NCP in early 2016 and finalized its Final Statement on 18 May 2016. descarga el pdf (867Kb)  
2 March 2015 National Contact Point France declaración This is a follow-up statement by the French NCP to its June 2013 Final Report and 17 March 2014 follow-up statement. descarga el pdf (710Kb)  
17 March 2014 National Contact Point France declaración French NCP follow-up statement announcing that an independent body to monitor the action plan has been selected by the parties. descarga el pdf (355Kb)  
19 June 2013 National Contact Point France declaración French NCP issues final statement. descarga el pdf (136Kb)  
24 August 2011 National Contact Point France aceptar The French NCP has accepted the complaint  
7 December 2010 Association Sherpa presentar Complaint filed at Belgian, French and Luxembourg NCPs descarga el pdf (468Kb)  